(建筑工程管理)施工测量
放线方案(阿海珐)
目录
壹、编制依据:············································2
1-1、图纸依据:········································2
1-2、测量依据:·········································2
1-3、规程依据:·········································2
二、工程概况:·············································2
三、测量人员及仪器配置:···································3
四、内业准备:··············································4
人员培训··········································4
图纸阅读···········································4
五、平面控制············································5
基础部分的平面控制;·······························6
轴线投测;·········································6
基槽开挖;·········································7
基础撂底;·········································7
六、高程控制:············································8
七、地脚螺栓测量·········································8
八、柱子安装时的测量:·····································10
九、吊车梁安装测量:·······································11
十、测量管理制度:········································12
十壹、测量监控及验线:····································12
壹、编制依据
.图纸依据:
施工总平面定位图、工程设计图纸目录如下:
序号 图纸名称 图纸编号
1 总平面布置图
.测量依据:
中国新时代国际工程 X公司提供的临时水准点及平面坐标成果表
1.平面坐标系统:武汉城市坐标系.
Xm01:x===
Xm02:x===
:x==定位点 1○1
:x==定位点 2○2
:x==定位点 3○3
2.高程系统:1985国家高程基准.
.规程依据:
《工程测量规范》(GB50026-93)
二:工程概况
本工程位于武汉阳逻经济开发区宝露棉 X公司南侧,东邻余泊北路,南侧
约 700米处为汉施公路。工程占地面积为 平方米,建筑面积约 37000
平方米。单位工程项目有钢结构联合厂房、办公楼及其他附属设施,
主厂房概况
厂房主体单层,平面上分五个区,A区跨度 35m,B区五跨跨度分别为 23m、
21m、21m、27m、,C区三跨跨度分别为 18m、33m、18m,D区跨度 18m,E
区跨度 25m,厂房内局部俩层,±标高对应的绝对高程为 ,建筑高度
~,试验站高度 ,结构形式为钢排架钢框架结构。
办公楼概况:
办公楼为三层现浇钢筋砼框架结构,平面呈“L”形,东西方向长度为
,南北方向长度为 ,±标高对应的绝对高程为 ,女儿墙顶
高度 ,,屋面高度为 ,壹至三层层高分别为 、、。
三:测量人员及仪器配置
本工程项目基础部分是桩基础,独立基础,大小不壹,每壹条轴线的放线必
须准确,才能确保整个区域工程位置准确,布置相接合,较为复杂,因此施工定
位放线应加强管理。测量放线准确和否是保证施工质量的前提和基础,要从全局
出发,处处为业主着想,积极配合业主和监理工作。为保证放线工作按时、按质
顺利完成,再结合本工程的特点及项目部人员的组织情况,首先设置测量班长壹
名,下设二名专业的放线员,总体负责整个工程的测量工作,然后每个区由施工
作业队选派 2-3人组成测量小组,经理部配备仪器如下。(各区的施工作业队的
测量仪器根据各区的需要配备数量足够的测量仪器)所有人员均要求持证上岗,
所有的测量仪器必须经过武汉市法定计量单位检验校准,且确保使用时在有效检
测期限内。
项目部人员配置
人员 职务 分工 备注
俞延军 测量负责人 主管放线
项目部仪器配置清单
仪器名称 型号 精度 数量 备注
全站仪 GTS-330W 2”、(3+2D) 1 已检定
经纬仪 DJ2 2” 1 已检定
水准仪 DSZ2 S3 2 已检定
钢尺 50m mm 2 已检定
四:内业准备
人员培训
施工前,由项目总工组织项目部技术工程师、测量人员认真学习测量规范、
规程,熟悉各种位置的测量、测设方法。且对本工程的测量进行交底,明确测量
要求,且对本工程的各部位测量工作作出具体的安排。测量作业的要求如下:
1、 严格执行审核原始数据的正确性,坚持测量工作步步校核,坚持自
检、互检、交叉检的制度,合格后由技术工程师验线。
2、 遵循“从整体到局部”、“先控制后碎部”、“高精度控制低精度”的
工作程序:
3、 测量记录要及时,数字正确、内容完整、字体工整、清楚、原始依
据正确;
4、 测量计算的基本要求:依据准确、计算有序、方法科学、步步校核、
结果可靠,记录中数字的位数反映观测的精度。
5、 测量结果现场标识要统壹、明确,确保不让施工现场任何相关人员
误解。
6、 测量人员必须明确为工程服务的目的,对按图施工和工程进度负责。
工作必须紧密配合施工,发扬团结协作、认真负责的工作作风。测
量人员必须要虚心学习、及时总结经验,发扬开创进取的创新精神。
图纸阅读:
测量必须以图纸为依据,在测量作业前必须熟悉图纸,对施工图中每壹结构
的形状、尺寸、位置都要了如指掌。
同时,对于工程施工中,由项目部资料员负责将工程的设计变更、洽商及时
送测量组,测量人员对变更内容需仔细查对,且将变更内容标识到图纸上,施工
现场按变更后的放线。
测量基准点的校核及保护:
本工程的定位,由中国新时代国际工程 X公司提供的施工控制成果表坐标点
及水准点,使用前,为保证建筑定位依据点的准确可靠,需对基准点进行内业核
算和外业校核。无误后将基准点保护好,由于机械,地下水等的影响要经常复核
保证规范的要求.
五:平面控制
基础部分的平面控制
1.平面控制
根据总平面图建立主厂房的轴线定位点定出轴线控制点(1、2、3、4)和导
线控制点(A、B、C、D)建立控制网作为主厂房的主轴线和道路等的测量控制点
1,2,3,4控制办公楼的主轴线然后建立碎步轴线控制点,依据建筑物的轴线尺
寸,作为平面控制的首级控制。
平面控制网成果见附图
1主厂房导线控制网,轴线控制网图
2导线闭合计算表
3控制轴线闭合计算表
在施工中,能准确迅速地恢复各轴线的位置,以保证同壹条中线或轴线在各
层上投测的位置都能在同壹铅垂面内。在矩形控制的实测中,其四角顶点用经纬
仪测每角的顶角为 90°;每角用 2个测回,其误差不得大于±9″~15″,四角的总
和为 360°,其误差不得大于±32″,四边的距离量距精度为 1/5000L。对平面控
制的四个顶点,设立牢固的标志。为防止施工过程中由于各种原因造成对标志的
影响,对四个顶点的观测要定期校核以保证测量的精度。
控制轴线控制桩的埋设距离边轴线的距离应适宜。视线良好,控制桩的埋设
做法如下图所示,且按图壹做好保护.
.基槽开挖:
根据轴线控制桩和基础平面图,按照技术交底及方案的放坡,撒出建筑物放
坡灰线,经自检、互检合格后,报监理工程师验线,为控制边坡位置,不造成超
挖或少挖现象,挖槽施工过程中测量人员要跟班作业,及时掌握好挖土深度和坡
底位置、控制好坡度。开挖每壹层土之前,测量人员要根据坡度,确定坑底边线;
挖完壹层后,测量人员要用线坠和塔尺确定修坡位置,指导工人修坡。
.基础撂底:
首先校测轴线控制桩,经闭合校核后,把轴线引测到基坑边,做临时点。临
时点周围砌砖保护,每次引测之前要对其进行复测,误差在 13"之内方可使用。
然后把经纬仪安置在该点后视控制点,用全站仪进行角度,距离闭合,精度要求:
角度观测 13",边长控制在 1:10000。将主控轴线投测到龙门桩上,用红油漆标
识清楚,注明轴线名称。校核精度合格后测设细部尺寸.经自检、互检合格后,
报监理工程师验收后,用红油漆把主要轴线及桩基础位置线标出,指导施工。
六:高程控制
根据武中国新时代国际工程提供的工程水准测量成果,水准点 SM01SM02
的绝对高程(SM01==)为基准在施工现场附近稳固的地方根
据需要设置 4个标高控制点,作为施工标高测量的依据点。测量方法采用闭合
导线法。其闭合差小于±6mm(n为测站数)。按测站数成正比例进行闭合差平差调
整,使之各点都得出准确的高程数据。
高程测量成果附图
1.高程测量控制点附图
2.高程测量闭合计算表
高程测量
高程测量根据甲方的高程控制点引测,引测到施工现场道路周围,道路中
线上订刚钉用红三角标注,且以此来编号.形成闭和控制高程网。基础部分的标
高测量直接由标高控制点引测,施工时可将标高抄测在场区控制桩上以方便基
础的施工。
七.地脚螺栓测量
钢柱基础定位和基坑底层轴线投测方法均和混凝土杯形基础相同,其特点是
基坑较深而且基础下面有垫层以及埋设地脚螺栓。其施测方法和步骤如下:
.垫层中线投点
垫层混凝土凝固后,应在垫层面上投测中线点,且根据中线点弹出墨线,绘
出地脚螺栓固定架的位置(图 4-1),以便下壹步安置固定架且根据中线支立模板。
图 4-1地脚螺栓固定架位置
1-墨线;2-中线点;3-螺栓固定架;4-垫层抄平位置
投测中线时经纬仪必须安置在基坑旁(这样视线才能见到坑底),然后照准
矩形控制网上基础中心线的俩端点。用正倒镜法,先将经纬仪中心导入中心线内,
而后进行投点。
.地脚螺栓的安装和标高测量
根据垫层上和固定架上投测的中心点,把地脚螺栓安放在设计位置。为了测
定地脚螺栓的标高,在摸板的斜对角处引测同壹数值的标高点,且刻绘标志,其
高度应比地脚螺栓的设计高度稍低壹些。然后在角钢上俩标点处拉壹细线,以定
出螺栓的安装高度。待螺栓安好后,测出螺栓第壹丝扣的标高。地脚螺栓不宜低
于设计标高,允许偏高+5~+25mm。
.支立模板和浇灌混凝土时的测量工作
支模测量和混凝土杯形基础相同。重要基础在浇灌过程中,为了保证地脚螺
栓位置及标高的正确,应进行见守观测,如发现变动应立即通知施工人员及时处
理。
.用摸板木架安放地脚螺栓时的测量工作
模板和木架支撑牢固后,即在其上投点放线。地脚螺栓安装以后,检查螺栓
第壹丝扣标高是否符合要求,合格后即可将螺栓焊牢在钢筋网上。因木架稳定性
较差,为了保证质量,模板和木架必须支撑牢固,在浇灌混凝土过程中必须在基
础施工时,应把轴线控制点引测到各基坑的边缘,以便控制基坑及承台的尺寸和
位置,便于承台和预埋螺栓的定位。投测的轴线校核合格后,方可螺栓定位。
八.柱子安装时的测量
1.柱子安装的要求是保证平面和高程位置符合设计要求,柱身垂直。
2.钢柱吊装要掌握如下要求:基础面设计标高加上柱底到牛腿面的高度,
应等于牛腿面的设计标高。首先,根据基础面上的标高点修整基础面,再根据基
础面设计标高和柱底到牛腿面的高度算出垫板厚度。安放垫板要用水准仪配合抄
平,使其符合设计标高。
钢柱在基础上就位以后,应使柱中线和基础面上的中线对齐。
柱子立稳后,即应观测±0点标高是否符合设计要求,其允许误差应满足表 8-1
的要求。
柱子安装测量允许偏差表 8-1
测量内容 测量允许偏差(mm)
钢柱垫板标高 ±2
钢柱±0标高检查 ±2
预制钢筋混凝土±0标高检查 ±3
柱子垂直度
柱高 10m内,≤±10
10m之上 H/1000≤±20
注:H为柱子高度。
3.柱子垂直校正测量用俩架经纬仪安置在纵横轴线上,离柱子的距离约为
柱高的 倍,如图 8-2所示,先照准柱底中线,再渐渐仰视到柱顶,如中线偏
离视线,表示柱子不垂直,可指挥调节拉绳或支撑,敲打楔子等方法使柱子垂直。
经校正后,柱的中线和轴线偏差不得大于 5mm。柱子垂直度容许误差,按表 8-2
的规定,柱高 10m之上时,其最大误差不得大于 20mm。满足要求后,要立即灌浆,
以固定柱子位置。
图 8-2柱子垂直校正测量
在实际工作中,常把成排的柱子都竖起来,然后才进行校正。这时可把俩台
经纬仪分别安置在纵横轴线壹侧,偏离中线不得大于 3m,安置壹次仪器可校正几
根柱子。但在这种情况下,柱子上的中心标点或中心墨线必须在同壹平面上,否
则仪器必须安置在中心线上。
九吊车梁安装测量
吊车梁的安装测量,主要是保证吊车梁中线位置和梁的标高满足设计要求。
1.吊车梁安装时的中线测量
根据厂房控制网或柱中心轴线端点,在地面上定出吊车梁中心线(亦即吊车
轨道中心线)控制桩,然后用经纬仪将吊车梁中心线投测在每根柱子牛腿上,且
弹以墨线,投点误差为±3mm。吊装时使吊车梁中心线和牛腿上中心线对齐。
2.吊车梁安装时的高程测量
吊车梁顶面标高,应符合设计要求。根据±0标高线,沿柱子侧面向上量取壹
段距离,在柱身上定出牛腿面的设计标高点,作为整平牛腿面及加垫板的依据。
同时在柱子上端比梁顶面高 5~10cm处测设壹标高点,据此修平梁面。梁面整平
以后,应置水准仪于吊车梁上,检测梁面的标高是否符合设计要求,误差应不超
过±3~±5mm。
十:测量管理制度:
1、 各项测量施工完成后,测量人员应严格按照规范要求落实“三检”制
度,即:自检、互检、交接检的原则,确认合格后,提请项目主管工
程师进行验线。合格后报监理工程师验收,验收合格后方能进行下道
各工序的施工。
2、 各项资料应从工程施工开始,就有次序,壹次不漏地积累做好各项资
料,且由主管人员和各相关人员签字认可,使之符合技术资料整理的
要求。
3、 严格审核图纸尺寸,按图放线,明确树立为工程施工负责的态度,确
保工程施工进度。
4、 测量放线过程中,应遵守先整体后局部,先高级后低级的工作程序。
5、 施工测量中,严格审核依据点的正确性,测量记录应原始、正确、完
整、工整,计算依据正确,步步校核。
6、 积极配合施工,尽量利用施工间隙放线,为施工创造条件。
十壹:测量监控及验线
1)监控制度
测量人员必须具有有效的岗位证书,且报监理备案。
所有测量仪器必须具有有效的检定证书,使用过程中必须按《计量法》规定
的检定周期进行检定,且报监理备案。
施工前必须编制《施工测量方案》,且经技术部、监理审定同意后方可实施。
做好原始点位的保护工作,以便在施工中进行校核。
2)验线制度
每道测量放线工序完成后,必须进行预检,预检由测量小组组长组织,由验
线员、质检员、工长及放线人员共同参加,预检合格后填写《预检工程检查记录》,
且填写《施工测量放线报验单》,壹且交监理报验,经监理验收合格后,方可进
行下道工序的施工。